Answer the question
In order to leave comments, you need to log in
How to display a list of tasks in Redmine for which actions took place over a period?
What you need to explain with an example:
1) the task was created in January;
2) work on the problem and heated discussions took place in February;
3) closed the task in March.
You need to show a list of tasks on which any actions were performed in February.
Inappropriate solutions:
1) Filtering by the "Updated" parameter is not suitable, because it has the value of the date of the last activity on the task.
2) The "Actions" tab (/activity) is also not suitable, since all changes are directly logged there , and it is rather problematic to isolate a list of tasks from there, given the enormous volume of tasks and discussions on them.
Answer the question
In order to leave comments, you need to log in
The user can set the time interval, the list of tasks is displayed on the left side, the date is displayed on the top. To do this, you need to:
Set the number of months;
Set the starting date for the countdown (select the month and year from the drop-down lists);
Click Apply.
After that, the chart will be updated, and it will display the status of the tasks of the selected project for the specified period of time. If you set the wrong period of time that you needed, click Clear, and then repeat all the steps for building the chart, specifying the required time period.
In the report "Spent time" all this can be done.
In any task, click on the time spent, there is a report with the ability to filter.
Didn't find what you were looking for?
Ask your questionAsk a Question
731 491 924 answers to any question