I work with customers on a project basis, without a contract. I draw up a work plan and confirm it with the customer. In the plan, I take into account the time for editing and confirmation for each stage. There are such customers who do not care about the timing of the allocation for approval and delay the time as much as they want, so I spend my time waiting and my schedule for the next projects gets off. At the same time, at the end of the project, they still manage to make claims "the project was not delivered on time."
Question:
How to deal with such customers? How to avoid such situations in advance? And what to do when such a situation arises in the development process?
Share your experience.
Answer the question
In order to leave comments, you need to log in
I warn the customer about two unpleasant facts: Firstly, the prepayment is not refundable under any circumstances. Secondly, in the absence of a response from him within the agreed time frame, I abandon the project.
I work with customers on project payment, without a contract
Work step by step through secure transaction services. Money is reserved, for example, in one resource I send the work for verification, 3 days are given for acceptance, if the customer is missing, then after 3 days the order is automatically accepted and you receive payment.
Delivery-acceptance agreement, which describes the obligations and rights of the parties
I work with customers on project payment, without a contract