The "Installation date" field changes during work, how to set a task 1 day before?

CRM - Deal Card There is a Mounting Date
field It can be changed at the last moment, how to constantly read the value of the field and set a task 1 day before the Mounting Date ? If it’s just through the BP with waiting for the launch , then this functionality does not take into account changes in the field in the future (


Answer the question

In order to leave comments, you need to log in

1 answer(s)
V
Vyacheslav Zhgilev, 2021-11-23
@jazzz

The following thought came up...
BP...
Cycle - execution condition: field The task is set: No
Delayed start - 1 day
Condition - 1 day before Installation date - Set the task - Fill in the field The task is set: Yes - exit from the cycle
It turns out, the cycle turns on 1 time per day until the date of installation is 1 day.
I'll write back as I check)