Tasks in jira after switching to the status done (done) are not crossed out?

We rechecked all the settings, but after the task is transferred to the "ready" status, its name / task type is not crossed out. If you look at the general list, it is very inconvenient and visually not to distinguish between closed and open tasks

Answer the question

In order to leave comments, you need to log in

1 answer(s)
I
icef, 2020-01-16
@icef

Crossed out - when there is a resolution. Put a post-function on the transition to the ready status with a resolution change to done or something like that. Or hang a resolution field on the screen of this transition and make it mandatory by the validator.
Well, for already closed and not crossed out - fill in the resolution.