New task in an existing sprint?

Good afternoon.
We launched SPRINT, how, in the case of a new task (for example, a bug), how to deal with it methodologically correctly?
Backlog and move to a new sprint? (what if this bug is meant to be fixed in the current sprint?)
Add a task to the sprint?

Answer the question

In order to leave comments, you need to log in

1 answer(s)
V
Vadim Matkarimov, 2016-03-28
@KREGI

Depending on what agreements you have in the team, here everyone sets the rules himself, Agile only declares the main points of interaction.
I would always look at how this bug will affect the current sprint, and if the process breaks and the upcoming release falls out of the planned schedule, then I would move this bug to the backlog as an unfinished task marked as a bug in the next sprint. If this bug does not affect the time of the sprint and your developer undertakes to close it on time, then this is a justified risk.