P
P
pixik2015-09-23 11:37:31
Project management
pixik, 2015-09-23 11:37:31

How to work with subproject tasks in MS Project 2015 from the main project?

Good afternoon!
In MS Project 2015, I add subprojects to the main project (as separate project files), they have tasks. why can't I edit subproject tasks from the main project? After all, these subprojects are part of the main one. Or am I wrong?
Is there any approach to such problems?
When trying to move a subproject task from the main project, the following warning appears:
82feb17f3be1460287d5ef72aa705e05.png

Answer the question

In order to leave comments, you need to log in

1 answer(s)
G
George V., 2015-10-01
@georg28

You can move tasks only within one subproject (source file), i.e. the task cannot be transferred to the parent project or to the neighboring subproject, but it can be copied.

Didn't find what you were looking for?

Ask your question

Ask a Question

731 491 924 answers to any question