How to create a calendar plan in redmine?

in the organization we plan to implement redmine for project management, namely tracking the implementation of tasks, collecting statistical data on the work of employees, their workload, and visibility into the implementation of project stages. Basically, the work on the project lasts 1 year. Accordingly, all work is divided into stages. please advise how it is possible to organize task scheduling within the framework of the stages of the calendar plan (all stages have duration indicated) for the project using redmine

Answer the question

In order to leave comments, you need to log in

1 answer(s)
A
Andrey Pletenev, 2017-02-25
@Andrey_Pletenev

In Redmine, it is convenient to use the concept of a version for stages. Set a time limit for each version. All tasks related to this stage, refer to the corresponding version.
When you reach the specific tasks of management accounting, such as calculating profitability in the context of customers, contracts, projects and stages; resource loading planning; calculation of KPI programmers and project managers, etc., please contact me. There are ready-made Excel spreadsheets and instructions for recording and uploading data from Redmine.