How can I increase the cost of an hour in an existing project?
Agreed with the client to increase the cost of an hour (we have been working for a year, he is satisfied). But in the profile you can only DECREASE it)))))).
How can I change the hourly rate upwards? Or is it necessary to start a new contract (in this case, it makes no sense, because the percentage of upwork will eat up the increase)?
Thanks
Answer the question
In order to leave comments, you need to log in
Start a new contract. Upwork percentage won't eat anything, because it is calculated for all contracts of one client in total. Those. if on the first contract you reached a commission of 5 or 10%, then on subsequent contracts it will remain