Is it possible to build a procurement plan in 1C ERP not based on a production plan?
Please tell me, is it possible to create a purchase plan not on the basis of a production plan?
Can a purchase plan be based on a production plan that has not yet been approved? If the production plan changes, is it problematic to work with the purchase plan, does it need to be rebuilt right away?
Answer the question
In order to leave comments, you need to log in
Yes, in the plans there is an opportunity to push your request, which will fill in according to the necessary data.
Yes, you can and not approved.
In general, you are right, when changing the release plan, launch the formation of a purchase plan. It's more of a sequencing rule.