Answer the question
In order to leave comments, you need to log in
How to calculate the numerical characteristic of the degree of delay of tasks?
There is a list of tasks. Each task must be completed a few days before the start of the event (for example, 10 days, 8 days, etc.). Each task has priorities 1, 2, 3, respectively, low (can be done later), medium (better done on time), high (must be done on time) and the percentage of completion for a particular activity. It is possible that tasks are not completed on time. Let's say we have the following set of tasks:
Name | A priority | ... |
---|---|---|
Task_1 | one | ... |
Task_2 | one | ... |
Task_3 | 3 | ... |
Answer the question
In order to leave comments, you need to log in
Move delays up, highlight in red, sort by delay in days. A 90% completed task is not done at all. The case is not closed. Dot.
expectedPercent Complete=(Days elapsed)*100/(totalDays/priority)
expectedDelayDays=Days-totalDays elapsed/priority
If the difference between expected and actual is >0, turn on the alert.
Didn't find what you were looking for?
Ask your questionAsk a Question
731 491 924 answers to any question