Answer the question
In order to leave comments, you need to log in
Assigning a task to multiple Redmine users. Is there a solution?
Found a discussion www.redmine.org/issues/12579
But I see that the developers have not done anything about this.
Does anyone know a plugin or some solution that will solve the problem of placing a task on several performers at once?
Answer the question
In order to leave comments, you need to log in
Join my colleagues.
The easiest way is to follow the principle of "one task - one executor" and create subtasks for grouping parallel processing if you need control over a common task and status control over subtasks.
An exception is when executors must work sequentially on the task within the workflow, then it is not necessary to create subtasks, but the status scheme should reflect the workflow.
Although if you really want perversions, you can technically create one group using the mail server and assign it to the RM, but only one person will change the statuses at the time of the next update.
Tested, not really. Assigned to a group - one took it, changed the status from New to In Progress, and the second one cannot do the same, he can only change from In Progress to Resolved, but it is necessary that the developers can work on it in parallel.
There are tasks and subtasks, to learn how to distribute them correctly, the business of two projects, if you haven’t learned how to drive such a clumsy with pissing rags in the neck, let him go as a janitor.
Didn't find what you were looking for?
Ask your questionAsk a Question
731 491 924 answers to any question